March 25, 2009

Engineering Report

 

Borough of West Cape May

 

            USDA FY2003 Water & Sewer Replacement Project – Remote Water Meter Reading System:

 

  • Status: 
  • USDA has given approval to execute the construction contracts with In-Line Services, Inc., the lowest responsible bidder, in the amount of $96,805.00.

 

  • USDA has concurred with the award of the contract and a pre-construction meeting is scheduled for March 26, 2009 at 10:00 AM.

           

 

            NJDOT Municipal Aid

 

  • Grant application has been approved by NJDOT in the amount of $143,000.00.   Work includes reconstruction of Sixth Avenue beginning at CR 607 (Bayshore Road) and proceeding easterly.
  • All work has been completed.

 

  • Contractor has prepared and submitted final payment request and close out documentation.
  • Change order to be issued for down time on project.  This will be incorporated into NJDOT grant.

 

            Park Boulevard Bike Path:

 

  • Close-out package, with the CFO certification, was sent to NJDOT on February 23, 2009.  Subsequent to NJDOT approval, the Borough can draw down the remaining 25% of the grant monies.