January 5, 2011

Engineering Report

 

Borough of West Cape May

 

Emergency Generator – USDA FY 2008 Water & Sewer Replacement Project

  • Status: 
  • Generator to be delivered Friday, January 7, 2011.
  • Training session is scheduled for Thursday, January 13, 2011.

 

 

            USDA Water and Waste Application:

 

  • Status: 
  • Kickoff meeting was held with USDA on July 27, 2010.
  • Triad Incorporated delivered full application to USDA 9/3/10.
  • USDA has reviewed the application.
  • The application is in the “pipeline” for funding when funds become available.  Funding Allocation expected February-March, 2011.

 

            FY2011 NJDOT Trust Fund Municipal Aid Program:

  • Status: 
  • Applications were due August 13, 2010.
  • RV&W has submitted the Phase 2 Park Boulevard Bike Path for both Municipal Aid and Bikeway funding on July 28, 2010.
  • Borough has passed ordinances approving the submission of the applications.
  • NJDOT has ranked all submissions.  NJDOT has not established a date for the announcement of award.

 

            Sunset Boulevard Parking Lot:

 

  • Status: 
  • RV&W prepared and sent the topographic survey and property line survey to Mr. Ed Belski, P.E. for preparation of the NJDEP permit application.