February 10, 2010
Engineering Report
Borough of West Cape May
Park Boulevard Bike Path Phase II:
- R V & W prepared and submitted an application for NJDOT funding of Phase II, between Emerald Avenue and Central Avenue. NJDOT continues to review the applications. The Application was denied.
Emergency Generator – USDA FY 2008 Water & Sewer Replacement Project
- USDA has determined the purchase of an emergency generator for pump station power outages is an eligible expenditure.
- Borough has authorized Remington, Vernick & Walberg Engineers to proceed with Bid Documents.
- Borough to authorize advertisement for bids. Open bids on March 11, 2010.
USDA Water and Waste Application:
- Pre-application being prepared by Triad Associates.
- Tentative schedule
- Pre-Application Submission – On or before February 12, 2010
- Invitation to Submit Full Application – February 28, 2010
- Full Application Submittal – March 15, 2010
- USDA Grant/Loan Offer – April 15-May 1, 2010
- At present, USDA is offering 30% grant and a 70% loan @ 2% interest for 40 years.
|
|
| 
Archival collection of Engineering Reports.
- Current Report
- July 14, 2010
- June 9, 2010
- May 12, 2010
- April 14, 2010
- March 10, 2010
- February 10, 2010
- November 11, 2009
- October 14th, 2009
- September 9th, 2009
- August 12th, 2009
- July 8th, 2009
- June 10th, 2009
- May 13th, 2009
- March 25, 2009
- February 25, 2009
- January 28, 2009
- December 17, 2008
- November 26, 2008
- October 22, 2008
- September 24, 2008
- August 27, 2008
- June 25, 2008
- May 28, 2008
- April 23, 2008
- March 26, 2008
- February 27, 2008
- January 23, 2008
- November 28, 2007
- September 27, 2007
- June 27, 2007
- May 23, 2007
- December 13, 2006
- October 25, 2006
- August 23, 2006
|
|