April 23, 2008

Engineering Report

 

Borough of West Cape May

USDA FY2003 Water & Sewer Replacement Project – Remote Water Meter Reading System (no change from March, 2008 report):

  • Status: 

 

  • USDA has been given preliminary approval to use their funds for the purchasing of the necessary hardware, software and meters. 
  • A meeting was held between the Borough and the City of Cape May to develop an intermunicipal agreement relative to sharing the remote water meter reading system.  Negotiations are underway.

 

  • System supplier has prepared equipment cost estimate for related equipment costs.  This information is essential to establishing the final scope off work to be completed.  Remington, Vernick & Walberg is working with Mark Blauer to determine the maximum amount of available funding.  Meeting was held with USDA Friday, January 11, 2008, to establish the procedure to move forward.  RV&W to prepare Scope of Work, to maximize the use of remaining USDA funds, and bidding process and forward to USDA for approval.  Additional work including replacement of pump station pumps and installation of meters by Contractor to be added to the contract.  Remington, Vernick & Walberg will then send a formal request letter to USDA for approval.
  • Borough has drafted technical specifications for the installation of the water meter.  Remington, Vernick & Walberg to review the specifications and develop the appropriate construction documents for bidding purposes.

 

            ADA Upgrades for the Municipal Building:

 

  • Scope of Work:  Modify the Municipal Building Complex and make it ADA compliant through upgrades to:  Parking area for spaces, sidewalks and ramps; Entrance and access doors including hardware throughout building; Accessible route to connect all accessible spaces;  Counter top and service window areas;  Alarm system including pull stations and visible strobes;  Bathrooms, drinking fountains and showers.

 

  • Status: 
  • All work is satisfactorily completed.
  • Contractor has satisfactorily completed all punchlist items.
  • Remington, Vernick & Walberg is preparing final close out paper work. 
  • Final payment requisition releasing retainage has been made.
  • PROJECT IS COMPLETE.

 

USDA FY2004 Water & Sewer Replacement Project - “Phase 2”:

  • Status: 

 

  • All work is satisfactorily completed.
  • Contractor has satisfactorily completed all punchlist items.
  • Remington, Vernick & Walberg is preparing final close out paper work. 
  • Final payment requisition releasing retainage will be forwarded to the Borough for review.

 

            NJDOT Municipal Aid:  

 

  • Grant application has been approved by NJDOT in the amount of $143,000.00.   Work includes reconstruction of Sixth Avenue beginning at CR 607 (Bayshore Road) and proceeding easterly.
  • The contract has been awarded to Albrecht & Heun, Inc.
  • NJDOT is reviewing the storm sewer replacement change order.  The Borough has requested NJDOT approval to use the entire grant amount by awarding the Change Order to Albrecht & Heun, Inc.
  • A letter from the Borough Solicitor supporting a change order to exceed the 20% maximum contract amount increase has been provided.  The Borough Resolution has been passed and awaits Borough signatures.  Upon signing of the Resolution (9/28/08), the package will be sent to NJDOT for approval.  Upon approval by NJDOT, Remington, Vernick & Walberg will process the change order and construction will begin.

 

            Park Boulevard Bike Path:

  • Schedule

Preconstruction Meeting                                  March 20, 2008
Begin Construction Date                                  March 31, 2008
Construction complete (60 days)                    May 9, 2008

    • Contractor has completed curb installation, milling and paving.