| 
March 26, 2008
Engineering Report
Borough of West Cape May
USDA FY2003 Water & Sewer Replacement Project – Remote Water Meter Reading System (no change from February, 2008 report):
- USDA has been given preliminary approval to use their funds for the purchasing of the necessary hardware, software and meters.
- A meeting was held between the Borough and the City of Cape May to develop an intermunicipal agreement relative to sharing the remote water meter reading system. Negotiations are underway.
- System supplier has prepared equipment cost estimate for related equipment costs. This information is essential to establishing the final scope off work to be completed. Remington, Vernick & Walberg is working with Mark Blauer to determine the maximum amount of available funding. Meeting was held with USDA Friday, January 11, 2008, to establish the procedure to move forward. RV&W to prepare Scope of Work, to maximize the use of remaining USDA funds, and bidding process and forward to USDA for approval. Additional work including replacement of pump station pumps and installation of meters by Contractor to be added to the contract. Remington, Vernick & Walberg will then send a formal request letter to USDA for approval.
- Borough has drafted technical specifications for the installation of the water meter. Remington, Vernick & Walberg to review the specifications and develop the appropriate construction documents for bidding purposes.
ADA Upgrades for the Municipal Building(no change from February, 2008 report):
- Scope of Work: Modify the Municipal Building Complex and make it ADA compliant through upgrades to: Parking area for spaces, sidewalks and ramps; Entrance and access doors including hardware throughout building; Accessible route to connect all accessible spaces; Counter top and service window areas; Alarm system including pull stations and visible strobes; Bathrooms, drinking fountains and showers.
- All work is satisfactorily completed.
- Contractor has satisfactorily completed all punchlist items.
- Remington, Vernick & Walberg is preparing final close out paper work.
- Final payment requisition releasing retainage was forwarded to the Borough for review.
USDA FY2004 Water & Sewer Replacement Project - “Phase 2”:
- All work is satisfactorily completed.
- Contractor has satisfactorily completed all punchlist items.
- Remington, Vernick & Walberg is preparing final close out paper work.
- Final payment requisition releasing retainage was forwarded to the Borough for review.
NJDOT Municipal Aid:
- Grant application has been approved by NJDOT in the amount of $143,000.00. Work includes reconstruction of Sixth Avenue beginning at CR 607 (Bayshore Road) and proceeding easterly.
- The contract has been awarded to Albrecht & Heun, Inc.
- NJDOT is reviewing the storm sewer replacement change order. The Borough has requested NJDOT approval to use the entire grant amount by awarding the Change Order to Albrecht & Heun, Inc.
- Remington, Vernick & Walberg requested a letter from the Borough Solicitor supporting a change order to exceed the 20% maximum contract amount increase necessary to replace the storm sewer and expend 100% of the NJDOT grant amount. If agreed to, by the Borough Solicitor, Remington, Vernick & Walberg will prepare the necessary change order and direct the Contractor to begin work.
- Borough Solicitor has requested letters from the contractor and RV&W certifying the need for the change order work. RV&W has drafted the requested letter and is working with the contractor to obtain the other letter.
Park Boulevard Bike Path:
Preconstruction Meeting March 20, 2008
Begin Construction Date March 31, 2008
Construction complete (60 days) May 9, 2008
|
|
| 
Archival collection of Engineering Reports.
- Current Report
- July 14, 2010
- June 9, 2010
- May 12, 2010
- April 14, 2010
- March 10, 2010
- February 10, 2010
- November 11, 2009
- October 14th, 2009
- September 9th, 2009
- August 12th, 2009
- July 8th, 2009
- June 10th, 2009
- May 13th, 2009
- March 25, 2009
- February 25, 2009
- January 28, 2009
- December 17, 2008
- November 26, 2008
- October 22, 2008
- September 24, 2008
- August 27, 2008
- June 25, 2008
- May 28, 2008
- April 23, 2008
- March 26, 2008
- February 27, 2008
- January 23, 2008
- November 28, 2007
- September 27, 2007
- June 27, 2007
- May 23, 2007
- December 13, 2006
- October 25, 2006
- August 23, 2006
|
|